Q4
2008 Summary
Ur-Energy
On Track for 2010 Production - Webcast Tomorrow
Denver, Colorado (Marketwire –
February 17, 2009) Ur-Energy
Inc. (TSX:URE, NYSE Alternext US:URG) (“Ur-Energy” or “the
Company”) is pleased to announce today that its permitting and engineering work
at Lost Creek continues to progress and that the Company continues to conserve
cash and adapt its financial projections so that the Company can achieve
production with the cash on hand.
Bill
Boberg, President & CEO stated, “Throughout 2008 Ur-Energy continued
to move further along the path towards production. Our permit applications are
progressing through the NRC and the WDEQ while our drilling, geologic and
engineering work continues on track. All detailed engineering designs
for our Lost Creek Plant and Mine Unit #1 are now complete and being prepared
for bid. We have reduced spending in non-critical areas and updated
our cash flow projections for Lost Creek to achieve production in late
2010.”
Management
of Ur-Energy invites you to join them for a Webcast at 11:00 AM Eastern Time,
tomorrow, Wednesday, February 18, 2009, to update interested shareholders on its
uranium project activities. Instructions for joining the Webcast are
as follows:
|
Date: Wednesday,
February 18, 2009
Time: 11:00 AM Eastern
Time
Dial-In
Numbers: Toll
Free - 1-888-679-8033
International
- 1-617-213-4846
Passcode: 40030122
Pre-Registration
for Webcast:
To
pre-register for the event use the following link:
https://www.theconferencingservice.com/prereg/key.process?key=PUBG98PCT
|
This call
is being webcast by ThomsonReuters and can be accessed at Ur-Energy’s website at
www.ur-energy.com. The
Webcast is also being distributed through the Thomson StreetEvents Network.
Individual investors can listen to the call at www.earnings.com.
Institutional investors can access the call via Thomson StreetEvents (www.streetevents.com),
a password-protected event management site.
HIGHLIGHTS
Corporate
The
latest financial results for Q3 2008 were released on SEDAR and EDGAR on
November 7, 2008. As of September 30, 2008 the Company reported cash
and cash equivalents and short-term investments of approximately C$66.0
million. The unaudited cash and cash equivalents
and
short-term investments as of December 31, 2008 were approximately C$65
million. Audited 2008 year-end financial results will be released by
the Company by the end of March 2009. The Company remains committed
to exercising budgetary control to allow its current cash position of
approximately C$65 million to be sufficient to move the Lost Creek Project into
production.
Lost Creek
Project
The Lost Creek uranium deposit is
located four miles north of Rio Tinto's Sweetwater mill in the Great Divide
Basin, Wyoming. The deposit is approximately three miles (4.8 kilometers) long
and the mineralization occurs in four main sandstone horizons between 315 feet
(96 meters) and 700 feet (213 meters) in depth. NI 43-101 Compliant Resources
(Roscoe Postle Associates Inc., June 15, 2006) for Lost Creek are: 9.8 million
pounds of U3O8 at 0.058%
as an indicated resource and an additional 1.1 million pounds of U3O8 at 0.076%
as an inferred resource. These resources are primarily in three
subdivisions of the HJ horizon with a small amount in the underlying KM
horizon. All pump tests completed to date have given
results which are considered positive for ISR mining.
The Lost
Creek Permit Area, which is specifically outlined in the applications to the
Nuclear Regulatory Commission (“NRC”) and the Wyoming Department of
Environmental Quality (“WDEQ”), consists of 201 unpatented mining claims and one
State of Wyoming section for a total of 4,220 acres (1708
hectares). The Company currently controls a total of 969 unpatented
mining claims and one State of Wyoming section for a total of approximately
20,740 acres (8,313 hectares), including the Permit Area within the Lost Creek
Project.
Ur-Energy’s
drilling objectives are to complete the delineation drilling, installation of
interior and exterior monitoring wells and pump test wells on up to three mine
units prior to the projected production startup in late 2010. Each mine unit
being developed within the area of the originally defined NI 43-101 resource
will have at least one million pounds of projected recoverable U3O8 within the
HJ sand horizon. Additional mine units will continue to be delineated after
production startup in both the HJ horizon and the underlying KM
horizon. All currently planned mine units are within the originally
defined NI 43-101 resource base of the Lost Creek Project.
Data for
564 historic drill holes on the project were reviewed when Ur-Energy started its
resource evaluation in 2005. Between 2005 and 2007 Ur-Energy drilled
287 holes for a total of 174,748 feet (53,263 meters). At the height
of the 2008 drilling operations, 7 rotary rigs and 3 geophysical logging trucks
were operating. During 2008, 459 drill holes were completed for a total of
303,040 feet (92,367 meters). Total drilling on the project to date
by Ur-Energy is 746 holes for a total of 477,788 feet (145,630
meters). Most of this drilling has been geared toward advancing the
primary resource in the HJ horizon at the Lost Creek deposit toward
production. For the most part, the detailed drill holes (300 to 400
holes to delineate each mine unit at 100 foot spacing) were drilled for mine
unit design and layout purposes. These holes are closely spaced for the mine
unit planning and specifically not for
the purpose of adding resources.
The
limited wide-spaced exploration drilling which has been completed to date has
defined several additional areas of potential KM horizon mineralization as well
as an entirely new uranium-bearing horizon, recently designated as the N horizon
as earlier reported (see Press
Release dated November 12, 2008). While requiring a major
exploratory drilling effort in the future to define actual resources (hundreds
of new holes per area), these new areas and horizons have strong potential to
increase the resource base of the project.
In 2009,
200 drill holes are initially planned. These include delineation drilling for
the HJ horizon in Mine Unit #2 as well as testing the extent and economic
potential of the underlying KM horizon both in Mine Units #1 and
#2. Also planned are regional baseline wells for the
KM
horizon
and the installation of KM horizon monitoring wells in Mine Unit
#1.
Ur-Energy’s
engineering staff, assisted by TREC Engineering completed detailed final designs
and specifications for all components of the Lost Creek ISR Plant and Mine Unit
#1 in January, 2009. Requests for bids are being prepared at this
time. Procurement will be ongoing in 2009 and construction at the
Lost Creek site will begin upon receipt of the necessary permits.
Ur-Energy
employed Petrotek Engineering to install a deep test well at the Lost Creek
Project. The well was drilled to determine the local stratigraphy,
geochemical and hydrologic data for the purpose of permitting a deep disposal
well for the production systems. The well was cased in 2008 and is
currently being completed to enable the Company obtain additional data on water
quality.
The NRC
and WDEQ permit applications are in the technical review phase with the Company
currently responding to technical questions from the
agencies. The NRC has notified the Company that questions
concerning the Environmental Report will be issued in the near
future. The Company does not anticipate any delays in the process and
currently expects the WDEQ Permit to Mine will be granted mid-year
2009. Ur-Energy expects to satisfactorily respond to all questions of
the NRC as soon as possible and in advance of June of 2009 when the Generic
Environmental Impact Statement for In-Situ Leach Uranium Milling Facilities
(GEIS) should be issued by the NRC. Unless site specific issues are
raised, with the aid of the GEIS, the NRC expects to complete the licensing
action, and issue the license, for the Lost Creek Project within two to three
months of the GEIS being issued.
Lost Soldier
Project
The Lost Soldier Project is
located approximately 14 miles (22.5 kilometers) to the northeast of the Lost Creek
Project. The property already has over 3,700 historic drill
holes defining 14 mineralized sandstone units. NI 43-101 Compliant Resources
(Roscoe Postle Associates Inc., July 10, 2006) for Lost Soldier are: 5 million
pounds of U3O8 at 0.064%
as a measured resource, 7.2 million pounds of U3O8 at 0.065%
as an indicated resource and 1.8 million pounds of U3O8 at 0.055%
as an inferred resource.
The
Company has elected to submit the NRC and WDEQ license applications for the Lost
Soldier Project after the Lost Creek license is granted. This will
allow the Lost Soldier Project to be included as an amendment to the Lost Creek
license(s). It is anticipated that the Lost Soldier licensing
effort will be streamlined and be more efficient as a satellite facility of the
Lost Creek Project.
Further
geological studies were initiated in late 2008 which focus on detailed mapping
of the roll-front geology. The studies will be followed by detailed mine design
planning and an NI 43-101 Preliminary Assessment which are expected to be
completed in 2009 prior to the completion of the permitting and licensing
applications as an amendment to the Lost Creek license.
W.
William Boberg, President and CEO, a Professional Geologist and Qualified Person
as defined by National Instrument 43-101, supervised the preparation of the
technical information contained in this release.
About
Ur-Energy
Ur-Energy
is a uranium exploration and development company currently completing mine
planning and permitting activities to bring its Lost Creek Wyoming uranium
deposit into production while also planning and permitting a
two-million-pounds-per-year in situ uranium
processing
facility. Ur-Energy engages in the identification, acquisition and
exploration of uranium properties in both Canada and the United
States. Shares of Ur-Energy trade on the Toronto Stock Exchange under
the symbol “URE” and on the NYSE Alternext US under the symbol “URG”.
Ur-Energy’s corporate office is located in Littleton, Colorado USA and its
registered office is in Ottawa, Ontario Canada. Ur-Energy’s website is
www.ur-energy.com.
FOR
FURTHER INFORMATION, PLEASE CONTACT:
|
Dani
Wright, Manager, Investor/Public Relations
|
Bill
Boberg, President and CEO
|
1-720-981-4588,
ext.
242
1-720-981-4588, ext. 223
1-866-981-4588
1-866-981-4588
dani.wright@ur-energyusa.com bill.boberg@ur-energyusa.com
This
release may contain “forward-looking statements” within the meaning of
applicable securities laws regarding events or conditions that may occur in the
future (e.g. production rates, timetables and methods at Lost Creek; receipt of
an NRC Source Material License, WDEQ Permit to Mine; the Lost Creek production
timeline and the Company’s financial status; the completion and timing of
exploration programs, etc.) and are based on current expectations that, while
considered reasonable by management at this time, inherently involve a number of
significant business, economic and competitive risks, uncertainties and
contingencies. Factors that could cause actual results to differ materially from
any forward-looking statements include, but are not limited to, capital and
other costs varying significantly from estimates; failure to establish estimated
resources and reserves; the grade and recovery of ore which is mined varying
from estimates; capital and other costs varying significantly from estimates;
production rates, methods and amounts varying from estimates; delays in
obtaining or failures to obtain required governmental, environmental or other
project approvals; inflation; changes in exchange rates; fluctuations in
commodity prices; delays in development and other factors. Readers should not
place undue reliance on forward-looking statements. The forward-looking
statements contained herein are based on the beliefs, expectations and opinions
of management as of the date hereof and Ur-Energy disclaims any intent or
obligation to update them or revise them to reflect any change in circumstances
or in management’s beliefs, expectations or opinions that occur in the
future.
Cautionary
Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred
Resources: The information presented uses the terms "measured", "indicated" and
"inferred" mineral resources. United States investors are advised that while
such terms are recognized and required by Canadian regulations, the United
States Securities and Exchange Commission does not recognize these terms. United
States investors are cautioned not to assume that all or any part of measured or
indicated mineral resources will ever be converted into mineral reserves. United
States investors are also cautioned not to assume that all or any part of an
inferred mineral resource exists, or is economically or legally
mineable.